The Brite Partnership secured planning permission in 2010 for a biomass development at the Firth Rixson Ickles Works at Templeborough where land and disused buildings where purchased in March 2011. The plant …
Rotherham Investment & Development Office – Online News
The £150m biomass-fired power plant project at Templeborough in Rotherham is starting to take shape
Peter Sills
T: 07976 437467
E: press@templeboroughbiomass.com
For everything else please click here to contact us.
Work has started on the new renewable energy plant within the industrial site at Ickles. The final planning permissions required to start work were received from Rotherham Council towards the end of …
We would like to welcome you to the first newsletter for the Templeborough Biomass Power Plant. We hope that this and the following newsletters will help to keep you up to date …
B&W Vølund’s consortium partner, Interserve Strategic Projects, will construct the plant for the developer, Copenhagen Infrastructure Partners. The Rotherham Biomass Plant will feature a B&W Vølund-designed multi-fuel boiler with a DynaGrate® fuel combustion system, …
Construction programme Construction on the brownfield site started on 15th March 2015. The plant first burned wood in May 2018 and first generated clean, green electricity in July 2018. Here’s how …
Templeborough Biomass Power Plant understands the importance of their role in supporting and benefiting the local community. The development of new jobs in the area is one of these key benefits. During …
Renewable Energy in the UK Our project and other renewable energy providers such as wind are all working towards achieving the UK Governments 2020 renewable energy targets and ensuring that the UK …