The Templeborough Biomass Power Plant project continues to make rapid progress, not only has the skyline changed with the construction of the power plant, but now a new bridge has been installed across the River Don at the site

Over the Bank holiday weekend of Saturday 28th to Monday 30th May 2016 the old bridge on the site of the new Templeborough Biomass plant was lifted out and a new bridge craned into position. The new bridge was lifted in as a single piece and weighs a mighty 153 tonnes and is over 49 m long. The bridge has been assembled at the site during May by Reid Steel from Christchurch in Dorset.  The ‘Big lift’ took place overnight on 28th May with the old bridge being lifted out and transported away, the crane being used for this lift is a Liebherr LG1750 and has a maximum height of 136 m, there are only four of these in the UK.

Tim Forrest, General Manager of the project says “Building, transporting and installing a bridge of this magnitude is a huge task, but it is a key element to completing the Templeborough Biomass Power Plant, so it is ready to generate clean and green electricity in August 2017.”

Mr Forrest went on to say “Choosing the best time to carry out the bridge swap has been challenging, but all agreed the perfect time is when the traffic is at it lightest and will cause the least disruption to road users and residents alike, so the spring bank holiday weekend at the end of May was chosen. The actual big lifts took place overnight with a crane rated at 750 T and brought to site especially for this purpose on Thursday 26th ready for the lifts on 28th May”. It has been a great team effort by Reid, Interserve and its subcontractors, in particular Moortown, a local civil engineering company from Leeds, to get ready on time for this remarkable spectacle which was planned way back in late 2015.

Further information on the renewable energy plant and how it is working within the community are available in the Templeborough Biomass Power Plant project newsletters, which you can find here, and by contacting Tim Forrest, General Manager on 07756 674294 or info@templeboroughbiomass.com

 

Click here to download the pdf

 

Bridge Lift 2Bridge Lift 1Bridge Lift 3