The Brite Partnership secured planning permission in 2010 for a biomass development at the Firth Rixson Ickles Works at Templeborough where land and disused buildings where purchased in March 2011. The plant …
Rotherham Investment & Development Office – Online News
The £150m biomass-fired power plant project at Templeborough in Rotherham is starting to take shape
Peter Sills
T: 07976 437467
E: press@templeboroughbiomass.com
For everything else please click here to contact us.
Work has started on the new renewable energy plant within the industrial site at Ickles. The final planning permissions required to start work were received from Rotherham Council towards the end of …
We would like to welcome you to the first newsletter for the Templeborough Biomass Power Plant. We hope that this and the following newsletters will help to keep you up to date …
B&W Vølund’s consortium partner, Interserve Strategic Projects, will construct the plant for the developer, Copenhagen Infrastructure Partners. The Rotherham Biomass Plant will feature a B&W Vølund-designed multi-fuel boiler with a DynaGrate® fuel combustion system, …
According to the DECC, renewable electricity generation was 21.1 TWh during the first quarter, up 15 percent from 18.4 TWh during the same quarter of the prior year. Renewable energy capacity reached 26.4 GW …
Under the agreement, GDF Suez Energy UK, sister company to waste management firm SITA UK (which is currently rebranding as Suez), will buy all the electricity produced at the waste wood biomass …
The plant will be fired with locally sourced waste wood and have a capacity of 45 MW. The power output generated from the plant will be equivalent to the energy consumption of 70,000 …
Brite Partnership North East has handed the contract to build the 44.1MWe plant at the former Firth Rixson Ickles Works off Sheffield Road, Templeborough, to construction specialists Interserve. Denmark-based Babcock & Wilcox Vølund …
The Brite biomass-fired power plant has a capacity of 39.3 MW and will be fired with waste wood sourced locally in the UK. The power plant is expected to be in operation …